Answer (D) is correct.
Under process costing, as with job-order costing, the cost of a normal
level of spoilage is left in cost of goods sold. Thus, the cost of the
period’s normal spoilage must be allocated among all the units worked
on during the period, both those finished and those remaining in work-inprocess.
Abnormal spoilage is recognized separately as a loss.