Detailed Answer
Answer (A) is correct.
In the long run, these costs should be the same. In the short run, however,
they may differ because standard costs represent what costs should be,
whereas budgeted costs are expected actual costs. Budgeted costs may
vary widely from standard costs in certain months, but, for an annual
budget period, the amounts should be similar.