During Year 1, Tidal Co. began construction on a project scheduled for completion in Year 3. At December 31, Year 1, an overall loss was anticipated at contract completion. What would be the effect of the project on Year 1 operating income under the percentage-of-completion method and the completed-contract method?
Percentage-of-Completion.... Completed-Contract