Detailed Answer
Answer (A) is correct.
MRP is a push system, that is, the demand for raw materials is driven by
the forecasted demand for the final product, which can be programmed
into the computer. This is in contrast with just-in-time manufacturing,
which is a pull system, meaning items are pulled through production by
current demand, not pushed through by anticipated demand.