Detailed Answer
Correct answer: (B)
there was an under-recovery of overhead of £275
Actual overhead charged to business:
2,150 actual hours x £1.50 per hour labour absorption rate = £3,225
Actual overheads incurred - £3,500
As charged to business less than incurred
Under recovery of £3,500 - £3,225 = £275