Zero Defects is an element of the quality management philosophy that is a ______________ for all workers to be achieved ______________.
Detailed Answer
Correct answer: (C)
standard; at all times
2
Statistical sampling methods are valid for most projects, regardless of the lack of repetitive processes, because ______________.
Detailed Answer
Correct answer: (A)
projects rely on external vendors for products that must meet contractual specifications to conform to the requirements
3
One of the advantages of team work is:
Detailed Answer
Correct answer: (A)
It breaks down barriers between internal
4
Crosby approach to management is:
Detailed Answer
Correct answer: (B)
Absolutes of Quality Management
5
A histogram ordered by frequency of occurrence that shows how many results were generated by each identified cause is:
Detailed Answer
Correct answer: (B)
Juran Histogram
6
A series of consecutive points on the same side of the average is called:
Detailed Answer
Correct answer: (A)
Run
7
A structured tool, usually industry or activity specific, used to verify that a set of required steps has been performed is called:
Detailed Answer
Correct answer: (B)
Check list
8
Financial compensation is the primary motivational tool for which of the following management theories or programs?
Detailed Answer
Correct answer: (B)
Theory X management
9
The Pareto Principle is a technique used by quality managers to determine which quality control problems concerning a particular service or manufacturing process should be corrected. Which of the following statements best represents the philosophy employed by this principle?
Detailed Answer
Correct answer: (B)
The majority of defects are caused by a small percentage of the identifiable problems. Improvement efforts should be reserved for those few vital problems