The key process input variables (KPIV) and key process output variables are developed during the ______________ phase.
Detailed Answer
C
3
An unbiased dice is rolled once. The probability of getting a number greater than 4 is:
Detailed Answer
D
4
Which of the following statement is false:
Detailed Answer
D
5
Cause and Effect Diagram can be used in the ______________ and ______________ step of DMAIC.
Detailed Answer
C
6
Which of the following is false regarding when acceptance sampling is useful:
Detailed Answer
B
7
Let p0 be the incoming fraction defective and p1 be the outgoing fraction defective (Assume both p1 and p0 is greater than 0). If rectifying inspection is performed then:
8
A company wants to measure the length of a fan as a part of its quality control exercise. The type of data collected will be:
Variable
Attribute
Detailed Answer
Detailed Answer
B
Cannot be determined
None of the above
9
If only ______________ causes of variation are present, the output of a process forms a distribution that is table over time and is predictable.
Assignable
Non-Random
NaturalDetailed Answer
Detailed Answer
C
Cannot be said
10
For an x bar chart, β risk can be defined as:
The probability of detecting the shift in process mean from μo (in control value) to μ1
The probability of not detecting the shift in process mean from μ0 (in control value) to μ1
Detailed Answer
Detailed Answer
B
The probability of detecting the shift in process range from μ0 (in control value) to μ1
The probability of not detecting the shift in process range from μ0 (in control value) to μ1