Process B had no opening inventory. 13,500 units of raw material were transferred in at Rs 4.50 per unit. Additional material at Rs1.25per unit was added in process. Labour and overheads were Rs 6.25 per completed unit and Rs 2.50 per unit incomplete.
If 11,750completed units were transferred out, what was the closing inventory in Process B?