Detailed Answer
Answer (C) is correct. The budget (spending) variance for fixed O/H equals actual minus budgeted fixed O/H. The $324,000 cost of supervisory salaries is fixed and is incurred at $27,000 per month. Thus, the variance is the difference between actual costs of $28,000 and the bud of $27,000, or $1,000 unfavorable.